Connection Application to the Lower Rontal Water Supply
- 29 October 2025
- 100%
- Permanent position
- Root
Job summary
The application for water supply connection in Root is vital. This is a chance to ensure proper water access for new buildings.
Tasks
- Submit a connection request for water supply per building.
- Provide details on water consumption and required installations.
- Ensure compliance with SVGW guidelines for plumbing installations.
Skills
- Experience in building project management or architecture.
- Strong understanding of water supply systems and regulations.
- Excellent communication and organizational skills.
Is this helpful?
About the job
To be filled out by the WV: Application No. / EntryConnection application to the Lower Rontal water supply
(Submit one application per building to the office)
The applicant(s) request connection to the Root water supply network for:
Object:
(Multi-family house, single-family house, residential and commercial building, commercial building; new construction, extension, conversion, etc.)
Parcel No.
Land register Root building insurance no.
(GVL)
Location designation, street, no., possibly building designation:
1. Involved persons / companies (name and first name or company, address)
Applicant / builder:
Tel.
Architect:
Tel.
Sanitary planner:
Tel.
Sanitary contractor:
Tel.
(if known)
Correspondence address:
Builder
Architect
2. Information on the expected water consumption: (according to sanitary planner)
Installations in the building must be carried out according to the W3 guidelines (incl. E3 09/2020) of the SVGW
Request our pressure device!
(mario.portmann@gemeinde-root.ch, +41 79 550 00 86, Mario
Portmann BM)
Normal installations: (e.g. apartments, office, commercial)
Total load values
LU largest individual load value
LU
Number of apartments:
Number of commercial enterprises:
Additional systems:
Rainwater use
Swimming pool
Pressure boosting system additional private water connection
Water treatment system
Special installations: (in addition to normal consumption e.g. continuous or peak consumption)
Max. required volume flow industry / commerce / sports facilities l/s
3
Max. required daily consumption commerce/industry (only if>10m /day) m3/d
Fire extinguishing facilities with water: (according to GVL requirements)
None
Small extinguishing posts (connection line max. DN 32)
Number
Indoor hydrant (connection line min. DN 40)
Number
Sprinkler system: required volume flow l/s
3. Dates:
Expected start of construction:
Commissioning:
4. Remarks:
Lower Rontal Water Supply Platz 1a
T 041 455 56 91
6039 Root D4 mario.portmann@gemeinde-root.ch www.gemeinde-root.ch
5. Documents: (paper form or by e-mail in PDF format)
Connection application signed on all sides
Situation (land register plan)
1:500 500
Floor plans of all floors (with location of distribution battery)
1:100 or 1:50
Section plans
1:100 or 1:50 each
For fire extinguishing facilities with water GVL order
Place:
Date:
Applicant / builder:
Property owner:
Architect / planner: